This document records the convergence characteristics the
PowerApps Optimal Power Flow [OPF]. The load flow [LF] and the OPF are carried
out sequentially till there is no further improvement in the performance
objective or feasibility of the solution. The cycles of LF and OPF are
identified as ADC in the tabular reports.
Two objective Functions are considered for illustration. The
first one, only the transmission loss minimization is considered. In the second
one, combined objective of economic dispatch and loss minimization are
considered.
PowerApps solves the economic dispatch and transmission loss
minimization as two phase optimization process as explained in the following.
1. Obtain initial
feasible load flow results
2. Step 1 gives
total generation requirement with transmission losses. Use this information for
economic dispatch solution
3. Use results of
step 1 for reactive power optimization with transmission loss minimization [or
any other suitable objective] to determine control settings for reactive power
controls.
4. Implement the
solutions of steps 2 and 3 and go to step 1.
5. Repeat steps 1
to 4 till no further controls can be implemented [optimum point is reached] or
till specified number of load flow and optimization cycles covered.
The cost function model used by PowerApps for economic
dispatch is as
All generators are assumed to have the same cost function
model. All generators are assumed to be running. Consequently only the variable
costs associated with MW generation is minimized.d with MW generation is minimized.
The tabular convergence characteristics report for various
system has the following headings and corresponding meaning.
|
Column Heading
|
Description of the content in tabular
column
|
|
ADC
|
Load Flow Cycle Number, 0 is the base
case load flow, 1 ,2 etc are after Optimizing the Controllers at the end of
previous load flows 0,1 etc
|
|
PG Total[MW]
|
Total MW generation at the end of load
flow
|
|
PL Total[MW]
|
Total MW Load
|
|
P Loss [MW]
|
Total MW Loss [ The objective used was
minimization of transmission losses, this should be seen as improving]
|
|
VMAX [pu]
|
Maximum bus voltage at a bus in per unit
as identified by load flow solution
|
|
VMIN [pu]
|
Minimum bus voltage at a bus in per unit
as identified by load flow solution
|
|
Sv [pu]
|
Absolute sum of all over and all under
voltage violations in per unit. Reduction in this value implies improved
voltage profile.
|
|
Nv
|
Number of bus voltage violations.
Reduction in this value implies improved voltage profile.
|
|
Qcom[MVAR]
|
Total MVAR compensation
|
|
VariableCost
|
Variable Cost of Generation [in any
specified currency units, depending on cost model]
|
NUMBER OF GENERATOR CONTROLS = 2
NUMBER OF TRANSFORMER CONTROLS = 2
NUMBER OF CAPACITOR CONTROLS = 2
TOTAL NUMBER OF CONTROLS = 6
|
ADC
|
PG Total
[MW]
|
PL Total
[MW]
|
P Loss
[MW]
|
VMAX
[pu]
|
VMIN
[pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
146.612327
|
135
|
11.612327
|
1.1
|
0.855219
|
0.044781
|
1
|
0
|
3693.92537
|
|
1
|
144.307479
|
135
|
9.307479
|
1.1
|
0.955202
|
0
|
0
|
10.5
|
3639.027584
|
|
2
|
144.319266
|
135
|
9.319266
|
1.1
|
0.954126
|
0
|
0
|
10.5
|
3639.304769
|
|
ADC
|
PG Total
[MW]
|
PL
Total[MW]
|
P Loss
[MW]
|
VMAX
[pu]
|
VMIN
[pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
146.6123
|
135
|
11.61233
|
1.1
|
0.855219
|
0.044781
|
1
|
0
|
3693.925
|
|
1
|
143.9538
|
135
|
8.953771
|
1.1
|
0.955852
|
0
|
0
|
10.5
|
3599.887
|
|
2
|
143.7244
|
135
|
8.724368
|
1.1
|
0.955202
|
0.000013
|
1
|
10.5
|
3571.063
|
Notes:
1. Variable costs
are minimized with economic dispatch
2. With economic
dispatch losses also have reduced further.
NUMBER OF GENERATOR CONTROLS = 4
NUMBER OF TRANSFORMER CONTROLS = 7
NUMBER OF CAPACITOR CONTROLS = 4
TOTAL NUMBER OF CONTROLS = 15
|
ADC
|
PG Total [MW]
|
PL Total
[MW]
|
P Loss
[MW]
|
VMAX
[pu]
|
VMIN
[pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
2680.472
|
2620
|
60.47208
|
1
|
0.867126
|
0.656766
|
15
|
0
|
125740.6
|
|
1
|
2671.757
|
2620
|
51.75726
|
1.05
|
0.948671
|
0.001329
|
1
|
75
|
124992.5
|
|
2
|
2671.661
|
2620
|
51.66116
|
1.05
|
0.948813
|
0.001187
|
1
|
75
|
124984.2
|
|
ADC
|
PG Total
[MW]
|
PL Total
[MW]
|
P Loss
[MW]
|
VMAX
[pu]
|
VMIN
[pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
2680.472
|
2620
|
60.47208
|
1
|
0.867126
|
0.656766
|
15
|
0
|
125740.6
|
|
1
|
2668.741
|
2620
|
48.74097
|
1.05
|
0.951578
|
0
|
0
|
75
|
118690.2
|
|
2
|
2668.759
|
2620
|
48.75948
|
1.05
|
0.951667
|
0
|
0
|
75
|
118691
|
Notes:
1. Variable costs
are minimized with economic dispatch
2. With economic
dispatch losses also have reduced further.
NUMBER OF GENERATOR CONTROLS = 12
NUMBER OF TRANSFORMER CONTROLS = 23
NUMBER OF CAPACITOR CONTROLS = 21
TOTAL NUMBER OF CONTROLS = 56
|
ADC
|
PG Total
[MW]
|
PL Total
[MW]
|
P Loss [MW]
|
VMAX [pu]
|
VMIN [pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
2203.259
|
2049.87
|
153.3887
|
1.010935
|
0.749948
|
5.525923
|
51
|
0
|
54213.98
|
|
1
|
2169.692
|
2049.87
|
119.8221
|
1.05
|
0.923664
|
0.065156
|
6
|
266.904
|
53379.55
|
|
2
|
2164.465
|
2049.87
|
114.5953
|
1.05
|
0.951416
|
0
|
0
|
375.1516
|
53253.67
|
|
ADC
|
PG Total
[MW]
|
PL Total
[MW]
|
P Loss [MW]
|
VMAX [pu]
|
VMIN [pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
2203.259
|
2049.87
|
153.3887
|
1.010935
|
0.749948
|
5.525923
|
51
|
0
|
54213.98
|
|
1
|
2165.328
|
2049.87
|
115.4578
|
1.05
|
0.926642
|
0.049282
|
4
|
266.904
|
52731.02
|
|
2
|
2158.131
|
2049.87
|
108.2615
|
1.051578
|
0.954055
|
0.002966
|
4
|
364.3801
|
52280.68
|
|
3
|
2157.065
|
2049.87
|
107.1954
|
1.054449
|
0.94652
|
0.012911
|
8
|
364.3801
|
52210.73
|
|
4
|
2155.865
|
2049.87
|
105.9951
|
1.071999
|
0.952598
|
0.03088
|
8
|
320.4141
|
52175.45
|
|
5
|
2154.255
|
2049.87
|
104.3852
|
1.074034
|
0.946683
|
0.03885
|
7
|
302.552
|
52124.63
|
|
6
|
2153.81
|
2049.87
|
103.9396
|
1.074893
|
0.958409
|
0.048713
|
12
|
317.6971
|
52107.12
|
|
7
|
2153.727
|
2049.87
|
103.8568
|
1.056282
|
0.958623
|
0.021778
|
9
|
317.6971
|
52099.53
|
|
8
|
2153.652
|
2049.87
|
103.7817
|
1.057435
|
0.959246
|
0.020234
|
9
|
317.6971
|
52097.58
|
|
9
|
2153.562
|
2049.87
|
103.6917
|
1.074952
|
0.95944
|
0.045557
|
10
|
317.6971
|
52095.26
|
Notes:
1. Variable costs
are minimized with economic dispatch
2. With economic
dispatch losses also have reduced further
3. The algorithm went
on for full specified 10 number of load flow and optimization cycles with
marginal improvements in the latter cycles..
NUMBER OF GENERATOR CONTROLS = 26
NUMBER OF TRANSFORMER CONTROLS = 25
NUMBER OF CAPACITOR CONTROLS = 18
TOTAL NUMBER OF CONTROLS = 69
|
ADC
|
PG Total
[MW]
|
PL Total
[MW]
|
P Loss
[MW]
|
VMAX
[pu]
|
VMIN
[pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
4833.519
|
4643.89
|
189.6287
|
1.03
|
0.740645
|
3.027959
|
61
|
0
|
139108.1
|
|
1
|
4795.075
|
4643.89
|
151.1846
|
1.05
|
0.927916
|
0.127677
|
10
|
275
|
137096.3
|
|
2
|
4789.937
|
4643.89
|
146.0468
|
1.058903
|
0.94073
|
0.034106
|
7
|
290.5083
|
136831.9
|
|
3
|
4789.367
|
4643.89
|
145.4768
|
1.058903
|
0.941461
|
0.031383
|
10
|
295.5083
|
136802.6
|
|
4
|
4789.521
|
4643.89
|
145.6313
|
1.058903
|
0.941266
|
0.032697
|
9
|
295.5083
|
136810.2
|
|
ADC
|
PG Total
[MW]
|
PL Total
[MW]
|
P Loss
[MW]
|
VMAX
[pu]
|
VMIN
[pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
4833.519
|
4643.89
|
189.6287
|
1.03
|
0.740645
|
3.027959
|
61
|
0
|
139108.1
|
|
1
|
4788.748
|
4643.89
|
144.8576
|
1.05
|
0.929997
|
0.102979
|
9
|
275
|
131047.6
|
|
2
|
4785.032
|
4643.89
|
141.1423
|
1.068482
|
0.942649
|
0.063537
|
12
|
280
|
130853.6
|
|
3
|
4784.729
|
4643.89
|
140.8385
|
1.068482
|
0.945397
|
0.065103
|
13
|
280
|
130857.6
|
|
4
|
4784.716
|
4643.89
|
140.8263
|
1.068482
|
0.945329
|
0.063751
|
13
|
280
|
130839.3
|
|
5
|
4784.338
|
4643.89
|
140.4477
|
1.068482
|
0.945977
|
0.060669
|
14
|
280
|
130822.6
|
Notes:
1. Variable costs
are minimized with economic dispatch
2. With economic
dispatch losses also have reduced further
NUMBER OF GENERATOR CONTROLS = 22
NUMBER OF TRANSFORMER CONTROLS = 77
NUMBER OF CAPACITOR CONTROLS = 47
TOTAL NUMBER OF CONTROLS = 146
|
ADC
|
PG Total
[MW]
|
PL Total
[MW]
|
P Loss
[MW]
|
VMAX
[pu]
|
VMIN
[pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
4563.446
|
4275
|
288.446
|
1
|
0.637032
|
21.68275
|
245
|
0
|
172591.8
|
|
1
|
4496.877
|
4275
|
221.8772
|
1.05
|
0.933239
|
0.039275
|
5
|
296.9124
|
166570.9
|
|
2
|
4492.448
|
4275
|
217.4478
|
1.05
|
0.950973
|
0
|
0
|
370.7209
|
166176.5
|
|
3
|
4492.045
|
4275
|
217.0445
|
1.05
|
0.952069
|
0
|
0
|
394.4941
|
166140.7
|
|
ADC
|
PG Total
[MW]
|
PL Total
[MW]
|
P Loss
[MW]
|
VMAX
[pu]
|
VMIN
[pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
4563.446
|
4275
|
288.446
|
1
|
0.637032
|
21.68275
|
245
|
0
|
172591.8
|
|
1
|
4483.542
|
4275
|
208.542
|
1.05
|
0.93653
|
0.023548
|
3
|
296.9124
|
151933.7
|
|
2
|
4480.509
|
4275
|
205.5087
|
1.052389
|
0.951147
|
0.002389
|
1
|
355.0025
|
151692.3
|
|
3
|
4480.031
|
4275
|
205.0313
|
1.052895
|
0.952047
|
0.002895
|
1
|
380.7686
|
151657.1
|
|
4
|
4480.096
|
4275
|
205.0962
|
1.052876
|
0.949652
|
0.003224
|
2
|
380.7686
|
151689.3
|
Notes:
1. Variable costs
are minimized with economic dispatch
2. With economic dispatch
losses also have reduced further
NUMBER OF GENERATOR CONTROLS = 66
NUMBER OF TRANSFORMER CONTROLS = 138
NUMBER OF CAPACITOR CONTROLS = 590
TOTAL NUMBER OF CONTROLS = 794
|
ADC
|
PG Total
[MW]
|
PL Total
[MW]
|
P Loss
[MW]
|
VMAX
[pu]
|
VMIN
[pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
13222.2
|
12545.15
|
677.0469
|
1.021436
|
0.553079
|
79.19027
|
829
|
0
|
415815.1
|
|
1
|
13222.29
|
12545.15
|
677.1386
|
1.05
|
0.701053
|
11.32251
|
267
|
5237.901
|
433129.7
|
|
2
|
13173.37
|
12545.15
|
628.2183
|
1.05435
|
0.759467
|
2.142998
|
85
|
5706.414
|
431965.5
|
|
3
|
13168.13
|
12545.15
|
622.9804
|
1.088152
|
0.766347
|
1.755495
|
68
|
5776.631
|
431846.7
|
|
4
|
13167.27
|
12545.15
|
622.1214
|
1.086513
|
0.76956
|
1.715472
|
68
|
5776.631
|
431827.3
|
|
5
|
13167.53
|
12545.15
|
622.3756
|
1.086294
|
0.769564
|
1.695118
|
64
|
5776.631
|
431833.1
|
Notes:
1. The initial load
flow corresponds to infeasible [not converged] load flow and hence its variable
cost is not valid. Load flow solution at the point of minimum mismatch was used
for optimization solution.
2. Losses and
Variable Cost however, steadily improve from converged load flow solution of
ADC 1 and above.
|
ADC
|
PG Total
[MW]
|
PL Total
[MW]
|
P Loss
[MW]
|
VMAX
[pu]
|
VMIN
[pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
13222.2
|
12545.15
|
677.0469
|
1.021436
|
0.553079
|
79.19027
|
829
|
0
|
415815.1
|
|
1
|
13234.75
|
12545.15
|
689.5994
|
1.050258
|
0.702001
|
11.97724
|
276
|
5237.901
|
416831.6
|
|
2
|
13186.04
|
12545.15
|
640.8946
|
1.050674
|
0.758889
|
2.236873
|
86
|
5671.229
|
416152.7
|
|
3
|
13179.77
|
12545.15
|
634.6243
|
1.051316
|
0.7699
|
1.72662
|
63
|
5642.4
|
414490.6
|
|
4
|
13178.79
|
12545.15
|
633.6431
|
1.053028
|
0.772968
|
1.707763
|
62
|
5642.4
|
414252.3
|
|
5
|
13178.72
|
12545.15
|
633.5735
|
1.052937
|
0.772805
|
1.709201
|
62
|
5642.4
|
414220.1
|
|
6
|
13178.68
|
12545.15
|
633.5295
|
1.052962
|
0.77285
|
1.707772
|
63
|
5643.69
|
414219.2
|
|
7
|
13178.73
|
12545.15
|
633.584
|
1.052942
|
0.772815
|
1.707775
|
61
|
5642.09
|
414220.5
|
|
8
|
13178.7
|
12545.15
|
633.5527
|
1.052969
|
0.772863
|
1.705596
|
63
|
5643.803
|
414219.7
|
Notes:
1. The initial load
flow corresponds to infeasible [not converged] load flow and hence its variable
cost is not valid. Load flow solution at the point of minimum mismatch was used
for optimization solution.
2. Losses and
Variable Cost however, steadily improve from converged load flow solution of
ADC 1 and above.
3. Variable Costs
Improve better with this objective compared to plain loss minimization
objective.
4. Over voltages
are controlled better with this combined objective compared to plain loss
minimization objective.
NUMBER OF GENERATOR CONTROLS = 20
NUMBER OF TRANSFORMER CONTROLS = 23
NUMBER OF CAPACITOR CONTROLS = 11
TOTAL NUMBER OF CONTROLS = 54
|
ADC
|
PG Total
[MW]
|
PL Total
[MW]
|
P Loss
[MW]
|
VMAX
[pu]
|
VMIN
[pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
4047.642
|
3933
|
114.6419
|
1.05
|
0.713986
|
3.145116
|
54
|
0
|
107107
|
|
1
|
4023.298
|
3933
|
90.29814
|
1.05
|
0.944865
|
0.00914
|
2
|
260
|
106210.6
|
|
2
|
4023.792
|
3933
|
90.7917
|
1.05
|
0.971693
|
0
|
0
|
280
|
106228.5
|
|
3
|
4023.614
|
3933
|
90.61445
|
1.05
|
0.969762
|
0
|
0
|
280
|
106222.1
|
|
4
|
4023.245
|
3933
|
90.24471
|
1.050238
|
0.973029
|
0.000238
|
1
|
280
|
106208.5
|
|
ADC
|
PG Total
[MW]
|
PL Total
[MW]
|
P Loss
[MW]
|
VMAX
[pu]
|
VMIN
[pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
4047.642
|
3933
|
114.6419
|
1.05
|
0.713986
|
3.145116
|
54
|
0
|
107107
|
|
1
|
4018.345
|
3933
|
85.3453
|
1.05
|
0.947386
|
0.004102
|
2
|
260
|
104144.6
|
|
2
|
4019.783
|
3933
|
86.78281
|
1.05
|
0.973307
|
0
|
0
|
280
|
104185.7
|
|
3
|
4019.389
|
3933
|
86.38881
|
1.05
|
0.972943
|
0
|
0
|
280
|
104165.9
|
|
4
|
4019.641
|
3933
|
86.64112
|
1.05
|
0.970029
|
0
|
0
|
280
|
104180.1
|
|
5
|
4019.269
|
3933
|
86.26866
|
1.05
|
0.97416
|
0
|
0
|
280
|
104163.7
|
Notes:
1. Variable costs
are minimized with economic dispatch
2. With economic
dispatch losses also have reduced further
NUMBER OF GENERATOR CONTROLS = 14
NUMBER OF TRANSFORMER CONTROLS = 19
NUMBER OF CAPACITOR CONTROLS = 13
TOTAL NUMBER OF CONTROLS = 46
|
ADC
|
PG Total
[MW]
|
PL Total
[MW]
|
P Loss
[MW]
|
VMAX
[pu]
|
VMIN
[pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
3955.887
|
3770
|
185.8874
|
1.04
|
0.654134
|
8.09204
|
82
|
0
|
119355.2
|
|
1
|
3922.079
|
3770
|
152.0789
|
1.05
|
0.908798
|
0.298497
|
25
|
185.1513
|
117368.7
|
|
2
|
3916.141
|
3770
|
146.141
|
1.05
|
0.925086
|
0.061712
|
8
|
185.1513
|
117024.5
|
|
3
|
3915.149
|
3770
|
145.1491
|
1.05
|
0.928355
|
0.038809
|
7
|
193
|
116967.1
|
|
ADC
|
PG Total
[MW]
|
PL Total
[MW]
|
P Loss
[MW]
|
VMAX
[pu]
|
VMIN
[pu]
|
Sv
[pu]
|
Nv
|
Qcom
[MVAR]
|
Variable
Cost
|
|
0
|
3955.887
|
3770
|
185.8874
|
1.04
|
0.654134
|
8.09204
|
82
|
0
|
119355.2
|
|
1
|
3933.614
|
3770
|
163.6135
|
1.05
|
0.903117
|
0.415851
|
31
|
185.1513
|
112740.3
|
|
2
|
3928.594
|
3770
|
158.5938
|
1.05
|
0.921461
|
0.134894
|
14
|
193
|
112511
|
|
3
|
3925.758
|
3770
|
155.758
|
1.05
|
0.927761
|
0.026561
|
4
|
211.2418
|
112379.5
|
Notes:
1. Variable costs
are minimized with economic dispatch
2. With economic
dispatch losses also have NOT reduced further
The results for 8 systems starting from 6 bus test system to
1043 bus practical Indian Grid system, indicates the robustness and
dependability of the PowerApps OPF algorithm
In most cases as observed by this author , the combined
objective of economic dispatch and loss minimization was more effective, as
compared to only transmission loss minimization objective.
Optimal Power Flow Algorithm